请问有哪位合同英语高手帮我翻译一下以下一段话?

Ministry of Finance and Planning appointed a Committee to make recommendation on issues related to price escalation on Bitumen and Aggregate. The Committee has recommended as follows:

Bitumen

Constractor to be paid for all interim and final claims
either
· the actual cost incurred by them, additionally, on Bitumen, based on prices published by ICTAD
or
· the payments calculated as per ICTAD Formula, using Index M30
whichever is higher.

This decision is applicable only for the contract for which the old indices for Bitumen have been used as per theICTAD price fluctuation formula in calculating the price adjustment.
机器翻译就不要来忽悠了,谢谢。

Ministry of Finance and Planning appointed a Committee to make recommendation on issues related to price escalation on Bitumen and Aggregate. The Committee has recommended as follows:
由于沥青及沙石料的价格不断上涨,斯里兰卡财政与计划部专门委任一个委员会,针对该问题做研究并提建议。该委员会已提出如下建议:
Bitumen
Contractor to be paid for all interim and final claims , either
the actual cost incurred by them, additionally, on Bitumen, based on prices published by ICTAD or
the payments calculated as per ICTAD Formula, using Index M30 , whichever is higher.
沥青:
承包商在此之前及最后的所以要求,将根据以下两种方式之一获得补偿,数额以高者为准。
1.按建筑培训与发展协会(ICTAD)公布的沥青价格计算,实际增加的沥青成本,或
2.按ICTAD公式M 30指数计算的付款额。

This decision is applicable only for the contract for which the old indices for Bitumen have been used as per the ICTAD price fluctuation formula in calculating the price adjustment.
这项决定仅适用于使用沥青旧指数,按ICTAD波动价格公式计算价格调整的合同。
温馨提示:答案为网友推荐,仅供参考
第1个回答  2008-10-19
Ministry of Finance and Planning appointed a Committee to make recommendation on issues related to price escalation on Bitumen and Aggregate. The Committee has recommended as follows:
财政与计划部指定了一个委员会,就有关沥青和聚合物的价格调整引起的争议,提出(解决问题的)建议方案。该委员会已建议如下:

Bitumen 沥青

Constractor to be paid for all interim and final claims
制造商将承担所有的期间索赔和最终索赔费用。
either 或者
· the actual cost incurred by them, additionally, on Bitumen, based on prices published by ICTAD
由他们引起的实际费用,另根据国际贸易和发展会议出版物的价格确定。
or 或
· the payments calculated as per ICTAD Formula, using Index M30
whichever is higher.
计算出的支付款项,按照国际贸易和发展会议出版物的方案,使用索引M30,以较高的价格为准。

This decision is applicable only for the contract for which the old indices for Bitumen have been used as per theICTAD price fluctuation formula in calculating the price adjustment.
这一决定是只适用于合同在价格调整问题上,使用一直按照国际贸易和发展会议出版物的关于沥青价格波动方案的旧索引,进行价格调整计算。
第2个回答  2008-10-20
Ministry of Finance and Planning appointed a Committee to make recommendation on issues related to price escalation on Bitumen and Aggregate. The Committee has recommended as follows:
Contractor to be paid for all interim and final claims either the actual cost incurred by them, additionally, on Bitumen, based on prices published by ICTAD or •the payments calculated as per ICTAD Formula, using Index M30 whichever is higher.
This decision is applicable only for the contract for which the old indices for Bitumen have been used as per theICTAD price fluctuation formula in calculating the price adjustment.
财政部和计委指定某委员会就有关沥青和碎石料价格上涨情况提出建议,该委员会已建议如下:
合同立约人,就其所发生的沥青实际成本, 基于建筑培训与发展协会(ICTAD)所公布的价格,或根据建筑培训与发展协会公式计算出来的价格,采用M30指数或更高的指数,应取得所有临时的和最终的索赔款项。
该决定仅适用于在进行价格调整计算时,已根据建筑培训与发展协会(ICTAD)价格变动公式,采用了沥青的原有指数所签定的合同。
第3个回答  2008-10-19
大概的意思是:
财政和规划部任命了一个委员会提出建议,有关问题的价格升级的沥青和总结。该委员会已建议如下:

沥青

Constractor所要付出的一切临时和最终索赔

或者

实际费用由他们承担,此外,对沥青,价格的基础上出版的ICTAD



付款的计算公式为ICTAD ,利用指数M30

以较高者为准。

这一决定是只适用于合同的旧沥青指标已被用来作为每theICTAD价格波动的公式计算的价格调整。