1、The system will be accepted by GSMC after the following items are completed:
1.1 The system passed all of the process, equipment, safety and vender‘s specification and signed equipment manager.
1.2 All the important spare parts and PCBs are tested and calibrated with inspection reports.
2、After the equipment is well calibrated and running smoothly then the acceptance test can be started.
3 The acceptance items would be completed within 30 days after modification completed.
4 The service engineer should prepare a formal diary to record every events, actions, data, ...etc. which should be signed by GSMC responsible engineer
5 During the acceptance test, in case anything (component, PCB, module) fails, the related items of the tests should be re-tested.